Timeline

Following are approximate dates of key milestones related to the City’s review and approval of the Campus Enhancement Plan (CEP). Please note that the dates are approximates only, and therefore subject to change.
The timeline will be updated on an ongoing basis.

Milestone Date
New NOP, Revised Initial Study and Project Description submitted to City of Los Angeles Winter, 2006
Conditional Use Permit (CUP) application filed Summer, 2006
Draft EIR circulated for public comment
(comments due within 45 days)
November-December, 2006
City Prepares Final EIR Fall 2007
Planning Department Hearing Examiner public hearing December 13, 2007
Citywide Planning Commission public hearing Spring 2008
City Council public hearing Summer 2008
Mayor concurs on City Council action Within 10 days